Temples of The Church of Jesus Christ of Latter-day Saints

Temples Under Construction

There are currently 45 temples that are under construction. Once each temple is completed, it will be opened to the public for an open house before being dedicated for ordinance work.

Completed; public open house and dedication postponed until large public gatherings deemed safe
Preparing for dedication
Preparing for dedication
Construction completed; public open house and dedication not yet announced
Finalizing construction; public open house and dedication not yet announced
Interior and exterior work underway; lamp posts installed and trees planted
Exterior painting underway; landscaping the grounds; interior work progressing
Stained glass installation underway; landscaping progressing; stone cladding of steeple nearing completion; interior work underway
Temple spire and angel Moroni installed on August 20, 2021
Plastering and painting the exterior walls; interior work underway; hardscaping the temple grounds
Stone cladding of temple underway; meetinghouse brick nearly completed; pouring curbing and walkways
Exterior cladding completed; boarding window openings; framing interior
Cupola installed atop steeple
Pre-fabricated modules delivered to a staging site; temple foundation waterproofed and backfilled; meetinghouse wrapped in a vapor barrier
Monument sign panels installed; cupola frame covered in plywood and wrapped in weather barrier
Walls and floors poured
Precast stone cladding completed; framing interior; hardscaping the grounds and planting trees
Central spire frame installed; precast panel installation progressing
Groundbreaking ceremony held on 9 October 2021
Damp proofing the exterior walls; steeple frame installed
Exterior cladding well underway; temporary windows installed
Scaffolding erected around steeple; sheathing of upper levels continues; cladding the main level in stone; preparing for meetinghouse floor slab
Sheathing exterior; framing interior walls; installing roof deck; pouring major slabs for parking facility ceiling
Cladding of exterior progressing; installing doors; hanging drywall on interior
Cladding the exterior in stone; installing window frames; pouring curbing and sidewalks
Roof installed; framing interior; wrapping exterior walls in vapor barrier
Steeple framing underway; cladding the exterior; installing landscape structures
Steeple frame installed; framing roof
Heavy framing progressing
Exterior walls rising
Structural walls poured
Groundbreaking ceremony held on 18 September 2021
Excavation for foundation underway
Site preparation continues; building retaining wall forms for storm water management area
Installing the foundation
Retaining wall removed; earthworks continue
Installing the footings and foundation walls
Parking lot paved; pouring footings and foundation walls
Stake center and service center razed; site clearing and preparation underway
Site preparations continue ahead of footings and foundation
Digging utility trenches; preparing for footings
Site grading underway
Construction trailers on site
Groundbreaking ceremony held on 11 September 2021
Groundbreaking ceremony held on 11 September 2021