Temples of The Church of Jesus Christ of Latter-day Saints

Temples Under Construction

There are currently 54 temples that are under construction. Once each temple is completed, it will be opened to the public for an open house before being dedicated for ordinance work.

Preparing for public open house beginning 1 December 2022
Preparing for public open house beginning 25 March 2023
Preparing for public open house beginning 15 April 2023
Construction nearing completion; final landscaping and interior finish work progressing
Construction nearing completion; final landscaping and interior finish work progressing
Construction nearing completion; final landscaping and interior finish work progressing
Exterior lighting tests underway; construction barrier replaced with permanent fence; landscaping and interior finish work progressing
Landscaping and interior finish work progressing
Scaffolding removed; interior work underway
Exterior lighting tests underway; cladding entrance and steeple pedestal; installing ornamental fence and benches; landscaping progressing
Installing stained glass; landscaping and interior work progressing
Installing exterior lighting; landscaping almost finished; interior finish work underway
Landscaping and interior work progressing
Stone cladding completed; landscaping and interior work underway
Art glass installation begins; stone cladding underway; landscaping and interior work progressing
Stone cladding underway; hardscape and interior work progressing
Entrance plaza palm trees planted; curbing poured for east parking lot; installing ornamental fence; interior work progressing
Exterior painted white; header window panels installed; interior work underway; landscaping the grounds
Angel Moroni installed on November 16; cladding the exterior walls; roofing the steeple dome; installing hardscape; interior work underway
Angel Moroni installed on November 24, 2022; stone cladding underway; interior work progressing
Hardscaping the grounds; preparing to install moldings on exterior walls of temple; meetinghouse exterior completed
Parking area surfaced with base layer of asphalt; curbs and gutters poured; landscaping preparations underway
Stone cladding underway; hardscape and interior work progressing
Stone cladding underway; hardscape and interior work progressing; meetinghouse framed and sheathed
Stone cladding underway; interior work progressing
Stitching modules together; installing insulation; parking areas paved
Roof and steeple frame coated
Stone cladding underway; glass installed in window openings; hardscaping the grounds; interior work progressing
Sheathing and cladding underway; hardscaping the grounds
Stone cladding underway; hardscape progressing
Exterior cladding underway; early interior work progressing
Spire installed on top of steeple frame; building ancillary structures; hardscape progressing
Constructing structural walls for the temple and meetinghouse; roofing the housing buildings
Building structural columns and walls
Detailed excavation underway
Building structural walls and floors
Building concrete block structural walls
Framing the superstructure
Structural framing underway
Building the exterior walls
Structural framing underway
Forming the basement walls
Building the structural walls of the temple, meetinghouse, and ancillary building
Excavation underway
Building the substructure for the temple and ancillary building
Foundation installed; framing the superstructure
Construction barrier erected; site preparation activities underway
Excavation underway
Construction underway
Construction underway
Building permits being issued; full-scale construction pending
Groundbreaking ceremony held on 20 August 2022; preparing for full-scale construction
Groundbreaking ceremony held on 8 October 2022; full-scale construction pending
Groundbreaking ceremony held on 26 November 2022; full-scale construction pending